DESIGN:  July 2014 - February 2016

PHASE 1 CONSTRUCTION:  Spring/Summer 2016 - Summer 2017 (Completed for September 2017)

PHASE 2 CONSTRUCTION:  Summer 2017 - Fall 2017 (Completed for October 2017)